Construction work is proceeding without disruption.
C, D, E: structure of the 2nd floor above the ground floor – 100%, 3rd floor – 50%.
A: walls and structure of the 4th floor above the ground floor. B: the same for the 5th floor above the ground floor. C, D, E: underground garage structure – 100%, slab over the garage – 75%, ground-floor walls – 60%.
A: walls and structure of the 3rd floor above the ground floor. B: the same for the 1st floor above the ground floor.
Rebar installation for the foundation slab has begun.
Progress as reported in the site updates: “–” means the update gives no figure for that building; 0% means the stage had not started yet (the update does not mention it). Use the arrows to browse each gallery; click a photo to enlarge it.